Dispute Review Boards: The Gun Without Bullets

In a post that I wrote early this year, I discussed the new, for India, concept of Dispute Review Boards. There I merely gave an overview of what the concept is all about, without resorting to any sort deep analysis, and the role of lawyers in such kind of proceedings. Though I wrote that post without actually attending in person any DRB proceedings, my opinions were based on the way in which everyone who is involved in it treated it, as an adjudicating process. My fears, in fact proved to be true beyond reproach as I got to attend one of the most hostile conciliation in my very limited experience. 

The problems in this particular DRB proceeding that I happened to involve myself are numerous. I can with a degree of certainty state that the same is the case with most other DRB proceedings in India. The fundamental problem is the mind-set that every person involved in the proceedings has towards the proceedings itself. As stated in my earlier post, lawyers contribute the most to this problem. Everyone involved in the proceedings thinks this merely as another box ticking exercise that has to be done before reaching the process of litigation, how much ever long drawn and adversarial it could be. This is no less because of the fact that none of the people who were involved in the process were either trained in the process or at least gone through the pain of reading the literature on this process. They essentially treated this like arbitration with a change in the nomenclature of certain things here, like an award in arbitration into recommendation. One of the important contributing reasons for this waywardness is the poor drafting of contractual clauses concerning the DRB. The contract that I was involved in, merely had two lines to the effect that the disputes should be first referred to a DRB and the process shall be governed by the ICC (International Chamber of Commerce) Dispute Board Rules. 

When to form?
The primary aim that is sought to be achieved through this conciliatory process is to solve any dispute in a commercial transaction as and when it arises and as amicably as possible. This has to be seen in the light of the fact that the whole concept Dispute Boards evolved as a solution for the problem of delay that happens frequently in the construction industry. To the contrary, in my case, the DRB process was initiated only after the whole project is over defeating the whole purport. In case the process is initiated post the completion of project, apart from the failure to resolve the disputes on time, it also results in a futile reconstruction of whole process again, wherein inevitably some muddling happens resulting in time and cost to the parties. A real time settlement more than settling the disputes helps preserving the relationship between the parties. An important reason for this mistake is because it has not been expressly mentioned in the contract, that the DRB has to be constituted at the beginning of the project, in order to continuously monitor the project and settle the disputes in real time.

Is It a Necessary Condition Precedent?
An interesting implication can be drawn if we suppose that a party bypasses the process completely and goes to litigate its claims. Though I was not able to find any Indian case law on this subject (Albeit it is a limited and indolent search of a lazy bone) I was able to find several American case laws, for the process has matured to a greater extent there. Two possibilities arise in such situations. One is where the claimant simply bypasses it and initiates litigation and another is where the other party simply insists upon the DRB proceedings to buy more time from litigation. The court (in BAE Automated Systems V. Morse Diesel International), as expected, ruled that, in the absence any legally justifiable reasons the process cannot be bypasses. The reasons can be waiver by one of the parties, fraud, estoppel etc. 

Appointment and Removal of Members
As in all conciliatory proceedings the integrity and impartiality of the person who is appointed as a member of the board is of utmost importance. It will be rhetoric to write about the code of conduct that a member of DRB must follow. In the proceedings that I happened to witness one of the members of DRB was visibly advocating the cause of the party who appointed him when the other party’s counsel made his oral presentation of his case. The reason could either be because he did not realise that it is a conciliatory proceedings and that he has to be impartial or because he is just a plain old jackass. The implications of such instances are very important, for any loss of confidence that a party has over the member will undermine the sanctity of overall process.

Applicability of Part III
I was curious after the incident, over whether the provisions of Arbitration and Conciliation Act, 1996, pertaining conciliation will be applicable in this case or not. It is given that it is a conciliation process; however it is still a creature of a contract. One possible reason can be that we cannot thrust in something which is not there already in the contract, with this essentially being a creation of the contract we cannot set it aside. However, Section 61 of the Act clears the air by defining its application and scope.

61. Application and scope - (1) Save as otherwise provided by any law for the time being in force and unless the parties have otherwise agreed, this Part shall apply to conciliation of disputes arising out of legal relationship, whether contractual or not and to all proceedings relating thereto. (2) This Part shall not apply where by virtue of any law for the time being in force certain disputes may not be submitted to conciliation.

I found an Indian case law that indirectly deals with the applicability of Part III of the act to the proceedings before DRB (Alcove Industries Ltd. Vs. Oriental Structural Engineers Ltd. [1]). The main issue in this case is the responsibility of an arbitrator to disclose in writing at the outset, such facts, which may give rise to justifiable doubts to his independence and impartiality. The arbitrator in this case, before being appointed as an arbitrator by the defendant company, worked as a member of Dispute Board, in respect of some works executed by respondent company. This fact was not disclosed when the appointment to the present arbitration proceedings were made. The court in order to explicate the bar of a conciliator (member of DRB in this case) referred to the provisions contained in Part III of the act. The judgement goes on to hold that section 80 of the act prohibits a conciliator from acting as an arbitrator or as a representative or counsel of a party in any arbitral or judicial proceeding in respect of a dispute that is the subject matter of the conciliation proceedings. Though these aspects are irrelevant for the present post, the important aspect that I can infer from this decision is the applicability of Part III of the act to the DRB proceedings. The decision, albeit indirectly, makes it clear that DRB proceedings are indeed governed by the provisions of the act.

Conclusion
Whatever is the form that the efforts for an amicable dispute resolution might take, it all ends up depending upon the intention and ability of the lawyers to best utilize the opportunity, more than the parties themselves, to settle the disputes in the most prudent way possible. The very intent of the process is defeated in most cases with things as basic as the tenor language that is used in the written communications. Without a fundamental understanding of such intricacies it is impossible for such efforts to succeed at any level. Moreover, in most cases with the resolution process being administered ad hoc without any institutional assistance, just like the case of arbitration, in India, the process loses its focus and the required streamlined approach without required expert assistance. The solution cannot be a something that can be done at the stroke of a pen. It requires some ideological acceptance of the process as a genuine alternative to settle the disputes. 


[1] 2008 (1) ARBLR 393 (Delhi)